Shelby Job Number | 199 |
---|---|
Project Name | 417 Widening – Narcoossee to SR 528/14 |
Project Location | Orange County, FL |
Prime Contractor Name | Sacyr Construccion SA, Inc. |
Superintendent for Project | Mike Wagner |
Years | 2 |
Days | 140 |
Project Details | The Central Florida Expressway Authority is widening State Road 417 (Central Florida GreeneWay) from Narcoossee Road to State Road 528 (Martin B. Anderson Beachline) to reduce congestion and improve traffic flow. This 4.7-mile project will add a lane in each direction, expanding the expressway from four to six travel lanes. Four sound walls are proposed in this segment. CFX will also be relocating the ramp plaza on the SR 417 ramp to Narcoossee Road and adding wider median shoulders that can temporarily accommodate additional traffic during emergency response events, such as traffic accidents or hurricane evacuations. This is on of five widening projects on SR 417 between International Drive and SR 528. |
Type of Work | Rebar and SIP Installation |
Rebar Quantity | 2,346,953 lbs |
SIP Quantity | 45,327 GSF |
Prime Contract Value | $92,279,567 |
Shelby Erectors Subcontract Value | $1,049,401.72 |
Online link to the project page | https://www.cfxway.com/wp-content/uploads/2020/05/UPDATED-10.21.2020-417-150-Fact-sheet.pdf |