62nd Blvd. Over Hogtown Creek
Shelby Job Number | 226 |
---|---|
Project Name | 62nd Blvd. Over Hogtown Creek |
Project Location | Alachua County, FL |
Prime Contractor Name | Leware Construction Co. |
Superintendent for Project | Ruiz, Manuel (RUIZMANU) |
Time frame for completion |
|
Years | 1 |
Days | 0 |
Project Details |
This 1.28 mile-long project consist primarily of new roadway construction to provide a new four-lane/two-lane corridor with bike lanes, sidewalk, and multi-use paths that connect SW 43rd Street and SW 20th avenue. The new connection also features construction of a new 270 foot-long bridge over Hogtown Creek. |
Project Scope |
|
Type of Work | Rebar and SIP Installation |
Rebar Quantity | 199,692 lbs |
SIP Quantity | 13,703 GSF |
Prime Contract Value | $72,000,000.00 |
Shelby Erectors Subcontract Value | $104,063.16 |
Additional Information | |
Online link to project page | https://wusfnews.wusf.usf.edu/transportation/2021-12-10/gainesville-and-fdot-are-moving-forward-with-building-a-road-to-try-to-decrease-i-75-congestion |