Shelby Job Number | 255 |
---|---|
Project Name | BP-477 People Mover – Airside 2&4 |
Project Location | Orlando International Airport |
Prime Contractor Name | Superior Construction |
Superintendent for Project | Vince Rankin |
Years | NA |
Project Details | The Orlando International Airport is replacing its Monorail/People Mover infrastructure. A total of 16,744 LF of monorail support will be constructed, connecting passengers between terminals. Shelby Erectors will install the Rebar, WWF, & Structural Steel scope. |
Type of Work | Rebar Installation |
Rebar Quantity | 403,000 lbs. |
Prime Contract Value | $NA |
Shelby Erectors Subcontract Value | $865K |