US 76 Over Wateree River
Shelby Job Number | 222 |
---|---|
Project Name | US 76 Over Wateree River |
Project Location | Richland & Sumter Counties, SC |
Prime Contractor Name | Zachary Construction Corporation |
Superintendent for Project | Cory Martin |
Time frame for completion | |
Years | 2 |
Days | 0 |
Project Details | The westbound bridge over the Wateree River will be replaced. The upgrade will improve safety along the route. |
Project Scope | |
Type of Work | SIP Installation |
Rebar Quantity | |
SIP Quantity | 92,400 GSF |
Prime Contract Value | $31,200,000.00 |
Shelby Erectors Subcontract Value | $144,539.30 |
Additional Information | |
Online link to project page |