I-75 Emergency Repair
| Shelby Job Number | 236 |
|---|---|
| Project Name | I-75 Emergency Repair |
| Project Location | Marion County, FL |
| Prime Contractor Name | Superior Construction Company |
| Superintendent for Project | Vince Rankin |
Time frame for completion |
|
| Years | 0 |
| Days | 30 |
| Project Details |
One bay of the SW 66th street Williams Road overpass will be demolished and reconstructed. |
Project Scope |
|
| Type of Work | Rebar and SIP Installation |
| Rebar Quantity | 4,072 lbs. |
| SIP Quantity | 598 GSF |
| Prime Contract Value | $1,500,000.00 |
| Shelby Erectors Subcontract Value | $10,500.00 |
| Additional Information | |
| Online link to project page | https://www.cflroads.com/news/article/52598/traffic-advisory-northbound-i-75-and-sw-66th-street-bridge-closure |