| Shelby Job Number | 255 |
|---|---|
| Project Name | BP-477 People Mover – Airside 2&4 |
| Project Location | Orlando International Airport |
| Prime Contractor Name | Superior Construction |
| Superintendent for Project | Vince Rankin |
| Years | NA |
| Project Details | The Orlando International Airport is replacing its Monorail/People Mover infrastructure. A total of 16,744 LF of monorail support will be constructed, connecting passengers between terminals. Shelby Erectors will install the Rebar, WWF, & Structural Steel scope. |
| Type of Work | Rebar Installation |
| Rebar Quantity | 403,000 lbs. |
| Prime Contract Value | $NA |
| Shelby Erectors Subcontract Value | $865K |