Shelby Job Number | 190 |
---|---|
Submission Type | New Project |
Project Name | Graham Swamp Trail |
Project Location | Flagler County, Florida |
Prime Contractor Name | Masci General Contractors, Inc. |
Superintendent for Project | Vince Rankin |
Years | 1.39 |
Days | 509 |
Project Details | The scope of work includes, but is not limited to the following: construction of a paved trail and elevated boardwalk in the Graham Swamp system from Lehigh Trail continuing south approximately 1.6 miles to SR 100, connecting with both the existing sidewalk along the north of SR 100 and a new proposed pedestrian bridge across State Road 100. The pedestrian bridge will continue to a connection with a proposed sidewalk along the south side of SR 100 to connect with the existing sidewalk along Old Kings Road. Improvements within the State Road 100 Right of Way will be constructed and inspected in accordance with FDOT Standard Specifications for Road and Bridge Construction. |
Type of Work | Rebar and SIP Installation |
Rebar Quantity | 256,319 lbs. |
SIP Quantity | 12,420 GSF |
Prime Contract Value | $Unknown |
Shelby Erectors Subcontract Value | $111,246.92 |
Online link to project page | https://www.visitflorida.com/listing/graham-swamp-preserve-trail/22019/ |