Project Name | Florida Turnpike Widening From SR 836 to NW 106th Street – FDOT Project E8R80 |
---|---|
Project Location | Miami-Dade County, Florida |
Type of Project | Rebar |
Prime Contractor Name | Halley Engineering Contractors, Inc. – Cone & Graham, Inc. (1st Tier Subcontractor) |
Years | 0 |
Months | 9 |
Days | 0 |
Project Details | Florida’s Turnpike Extension (SR 821) will be widened to 10 lanes, from Dolphin Expressway/SR 836 to NW 106 Street/Flagler Station Boulevard. The project entails converting NW 117 Avenue, between NW 34 Street and NW 41 Street, into a northbound Florida’s Turnpike entrance ramp and a slip ramp for local traffic continuing on NW 117 Avenue, north of NW 41 Street. |
Project Scope | Deck and Approach Slab Rebar Installation for Bridges 2,3,4,5&6 |
Additional Information | Rebar Quantity – 1,458,702 lbs. Prime Contract Value – $244,979,348 Shelby Erectors is a 2nd tier subcontractor to Cone & Graham, Inc. |